Office Building

Scope of supply:

  • BMS Controls
  • Panels
  • Power & Control Wiring
  • 480  x 4 pipe fan coil unit controls

Perhaps a more conventional control system but given a project programme of just over 4 Months to complete gave us a reasonable challenge to complete.

8 control panels manuactured to serve:

Riser outstation and monitoriing

Comms room AC control & monitoring

LV panel metering

Main Motor Control Centre to control:

  • 2 Chillers
  • 3 Boilers
  • 4 AHU's
  • WC plant

Practical completion reached on specified date !!